Inga:
Promise
MAY 18, 2004 Business In Africa
Online
The development of Inga-3 is now associated with
the Western Power Corridor (WESTCOR), a joint venture
company registered in Botswana. WESTCOR aims to
transmit power from Inga-3 in the DRC to South Africa
via Angola, Namibia and Botswana. Once the WESTCOR
Joint Venture Company is formed, equal equity contributions
from the five national utilities and their chosen
partners will make up the equity portion and security
package for the debt portion of the project financing.
International financiers will be encouraged to participate
and to take up debt financing. Considerable support
is also expected via the NEPAD initiative. There
are three main components in the implementation
of the WESTCOR project:
- The development of the Inga-3 power station
is estimated to cost US$3.74 billion
- Two 1,500MW converter stations will be constructed
at a basic cost of approximately US$421 million
each, totalling US$842 million. Upgrades for
the two existing stations along the lines will
be included in the HVDC installation cost.
- Converter stations - HVDC transmission lines:
The two South African termination points are
3,000 to 3,500 km from Inga-3. The total estimated
cost for the transmission lines, including the
terminations in South Africa, is US$652 million.
Inga site characteristics
Inga site is situated at a latitude of almost
six degrees south and 14 degrees east in the DRC.
It is about 150km upstream of the mouth of the
Congo River and 225km downstream from Kinshasa.
The Congo River, with an average flow rate of
42,000 cubic metres per second, is the second
largest river in the world after the Amazon. Among
the big rivers of the world, it is the only one
that has a significant slope in its lower course.
For instance, in a distance of 15km, the natural
difference in height is 102 metres. This series
of rapids makes the Inga site the biggest source
of hydro power in the world at a single point;
the unbridled energy passing the point amounts
to approximately 370 billion kWh per annum. Inga's
yearly minimum flow rate is not less than half
the annual maximum flow rate and this makes the
river stable and suitable for power generation.
The historical minimum flow rate was recorded
in 1905 and was 21,400 cubic metres per second.
The historical maximum flow rate, 84,400 cubic
metres per second, was recorded in 1961.
Development of the Inga site
The overall development of the site foresaw four
stages grouped into two phases. The first stage
was the use of the Nkokolo valley to its maximum
potential, while the second phase was the construction
of the Grand Inga. The Nkokolo valley scheme does
not require building a dam over the whole river.
It uses a disused river bed that is closed off
by the Shongo dam at the lower end. This gives
a head of 60 metres to a part of the water diverted
from the river at a point 8 km upstream. The scheme
involves three stages of development:
- Inga-1 Power Station (commissioned in 1972)
- Inga-2 Power Station (commissioned in 1982)
- Inga-3 Power Station (planned). The development
of Inga-3 is now associated with the Western
Power Corridor (WESTCOR) and will be described
in detail later in this article.
The Grand Inga scheme involves building a dam
across the whole river so as to divert all the
water into the adjacent Bundi valley, and the
total flow rate of 26,400 cubic metres per second
at its minimum can be used under a head of 150
metres to generate 39,000MW in total (52 machines
at 750MW each).
Export potential
Six power export corridors have been identified
for power transmission from the Inga site as follows;
western, northwestern, northern, northeastern,
eastern, and southern (Figure 3). The existing
Inga-Kolwezi HVDC and the AC network linking it
to Zambia, Zimbabwe, Botswana, and South Africa
forms the southeastern corridor. The western corridor
will link Inga to West Africa, to supply the potentially
large market in Nigeria, plus imports to the rest
of West Africa. The northern and northwestern
corridors will serve Morocco, Algeria, Tunisia
and Libya.
Planned rehabilitation of Inga
Existing power stations
The characteristics of the existing power stations
(Inga-1 and Inga-2) are given in Table 1. The
Societé Nationale d' Electricité (SNEL) of the
DRC owns and operates the two existing power stations,
Inga-1 and Inga-2, with a combined output of 1,770MW.
Characteristics of the existing power stations
|
Inga-1 |
Inga-2 |
Year of commissioning |
1972 |
1982 |
Water head [metres] |
50 |
58 |
Turbine flow [cubic metres per second] |
780 |
2,800 |
Number of machines |
6 |
8 |
Installed Capacity [MW] |
351 |
1,424 |
Expected Production [TWh/Year] |
2.4 |
10.4 |
Planned expansion
Inga-3 is the next phase of the development of
the Inga site, with a projected output of 3,500MW.
The final phase of the development will be the
Grand Inga, with a potential rated output of 39,000
MW.
Characteristics of the planned expansion
|
Inga-3 (WESTCOR) |
Grand Inga |
Water head [m] |
6,300 |
26,400 |
Turbine flow [cubic metres per second] |
50 |
58 |
Number of machines [MW] |
3,500 |
39,000 |
Expected Production [TWh/Year] |
23.5 |
288.0 |
The western power corridor
The Western Power Corridor project (WESTCOR)
is intended to exploit the environmentally friendly,
renewable, hydroelectric energy of the Inga rapids
site in the DRC. Load growth in the southern networks
has outstripped expectations as a result of energy-intensive
investments taking advantage of the excellent
quality of supply available in the SADC region
at internationally competitive prices. Studies
have shown that additional generating capacity
will need to be in regular commercial service
in the southern networks of the SAPP by as early
as 2007.
In addition, the Empresa Nacional De Electricidade
(ENE) of Angola reported that the hydroelectric
potential of the Cuanza Basin in northern Angola
is approximately 6,000MW. ENE expressed interest
in developing this resource and exporting the
energy to WESTCOR and other customers in SAPP.
An additional 2,500MW can be potentially captured
from gas presently flared off in the northern
Angolan oilfields. Elf Aquitaine and GEC Alsthom
did a preliminary scoping study during the mid-1990s
to export this available energy to South Africa.
The WESTCOR Joint Venture Company
The WESTCOR Steering Committee was formed under
the auspices of the SAPP to initiate studies determining
the viability of the Western Power Corridor with
the source at Inga-3. The WESTCOR Joint Venture
Company was registered in Botswana to fund the
engineering and financial studies, and to build,
own, and operate the infrastructure, should the
project prove to be viable. Each of the five participating
utilities contributed $100,000 as start-up capital
to fund the first phase of development.
Five utilities are participating in the project.
Each utility is represented on the Steering Committee
and will own 20 per cent of the share capital
of the proposed new joint venture company. The
utilities are:
- NamPower, power utility company of Namibia
- Eskom, power utility company of South Africa
- Empresa Nacional De Electricidade (ENE), power
utility company of Angola
- Societé Nationale d' Electricité (SNEL), power
utility company of the DRC
- Botswana Power Corporation (BPC), power utility
company of Botswana.
Environmental concerns
A complete Environmental Impact Assessment (EIA)
study is scheduled in the immediate future for
the twin HVDC lines serving as the interconnector
through DRC, Angola, Namibia, Botswana and South
Africa. Preliminary surveys, however, have not
identified any evident environmental risks in
the development of the project. Thus, it is anticipated
that any environmental concerns found in the study
will be easily resolved. Where the environmental
impact of Inga-3 is concerned, the Congo river
flow does not show seasonal variations to the
extent of other rivers in the Southern African
region, and is therefore sufficiently reliable
to enable the Inga site to be developed on a run-of-river
basis. The lack of variation in river flow is
due to the catchments area that straddles the
equator, and the seasonal rainfall patterns in
the northern and southern areas that are contra
cyclic to the river flow. This eliminates the
need for a costly large storage dam to compensate
for seasonal variations in river flow. In addition,
eliminating the need to flood large areas significantly
reduces the environmental impact. As a result,
energy from Inga-3 would qualify as green energy
in terms of the Kyoto Protocol on global warming,
and the sale of carbon credits to developed countries
could become an additional source of revenue for
WESTCOR.
WESTCOR customers
The primary customers of WESTCOR are expected
to be the SAPP member utilities. With Inga-3 producing
3,500MW for WESTCOR, distribution along the transmission
lines has been predicted according to the estimated
demand within each of the five participating countries.
Due to the cheap energy in Southern Africa the
WESTCOR project will attract industry requiring
high power consumption. Immediate examples are
those of the Hindalco smelter, which will relocate
from India to Walvis Bay in Namibia, as well as
the Al smelter for BHP Billiton in Coega, South
Africa.
This is a presentation by Mr. B. J. Mbuere
ua Mbuere from Nampower and Dr. Lawrence Musaba
from the SAPP Zimbabwe, presented at the Power
Generation Conference