een wereldwijd elektriciteitsnet een oplossing voor veel problemen  GENI es una institución de investigación y educación-enfocada en la interconexión de rejillas de electricidad entre naciones.  ??????. ????????????????????????????????????  nous proposons la construction d’un réseau électrique reliant pays et continents basé sur les ressources renouvelables  Unser Planet ist mit einem enormen Potential an erneuerbaren Energiequellen - Da es heutzutage m` glich ist, Strom wirtschaftlich , können diese regenerativen Energiequellen einige der konventionellen betriebenen Kraftwerke ersetzen.  한국어/Korean  utilizando transmissores de alta potência em áreas remotas, e mudar a força via linha de transmissões de alta-voltagem, podemos alcançar 7000 quilómetros, conectando nações e continentes    
What's Geni? Endorsements Global Issues Library Policy Projects Support GENI
Add news to your site >>







About Us

Giant dam projects aim to transform African power supplies

June 19, 2007 Sarah J Wachter International Herald Tribune

PARIS: As the world's political leaders debate ways to alleviate poverty in Africa, industrialists are moving ahead with their own designs for pan-African development - including the building of the world's largest hydroelectric dam at a bend in the Congo River, between Kinshasa, the capital of the Democratic Republic of Congo, and the Atlantic Ocean.

Called Grand Inga, this giant dam will cost $80 billion to build and will have twice the installed generating capacity of the current record-holder, the Three Gorges Dam in China. Grand Inga would produce enough electricity to serve all of the more than 500 million Africans who currently go without.

While it remains to be seen whether recent leaps in transmission technology are sufficient to carry electricity over Africa's vast distances and physical barriers like the blistering sands of the Sahara, power-hungry countries as far away as Egypt and Nigeria are interested in Grand Inga's potential supply.

"This is a Marshall Plan for Africa," said Gerald Doucet, secretary general of the World Energy Council, the overseer of the project, which is being developed with Westcor - a consortium of power companies from neighboring countries including Namibia, Angola and South Africa - and with international power and engineering giants, including ABB of Sweden, E.ON of Germany, EDF of France, Union Fenosa of Spain and SNC-Lavalin of Canada.

Grand Inga is one of a growing list of large dams under development or serious discussion in Africa, where private investors and development banks are re-examining the potential of "big hydro" to help counter a worsening power shortage.

The World Bank and its lending arm, the IFC, along with the African Development Bank, private investors, power companies and, increasingly, Chinese hydroelectric concerns are the major players.

The amount of hydropower under construction in Africa jumped 53 percent from 2004 to last year, according to the Hydropower & Dams World Atlas and Industry Guide, an industry reference journal. But environmental watchdogs and other nongovernment organizations say that, unlike oil and gas development, the planning process for hydropower lacks transparency and the number of dams under development in Africa is difficult to pinpoint.

Armed with a wealth of experience in constructing large hydro dams, Chinese companies are signing on to projects in many African countries, often as elements of infrastructure investment packages in oil-producing countries. For example, China plans to build and finance a $1.5 billion, 2,000-megawatt plant in the Mambila Plateau in Nigeria, in a deal that also includes Chinese imports of the country's oil and rights to exploit four oil blocks.

Apart from Chinese projects, the World Bank recently approved a $360 million package of loans and guarantees for Bujagali, a 250-megawatt hydro plant on the Nile at Lake Victoria in Uganda that will cost $799 million to build. Uganda, with the fastest growing population in East Africa, has regular rolling blackouts and only one percent of the rural population has access to electricity.

The World Bank also made a $297 million grant to refurbish two existing hydropower plants on a site near Grand Inga last month, as part of a $500 million package co-financed with the African Development Bank to repair damage and silting that occurred over the past decade, during Congo's civil wars.

"Interest in the importance of hydropower has been slowly re-emerging over the past five years," said Philippe Benoit, Inga project manager at the World Bank.

Large dams became controversial in the 1980s and 1990s as environmental and civil rights organizations focused attention on issues like the damage done to rivers, watersheds and aquatic ecosystems, poorly designed resettlement strategies, failure to share economic benefits with affected communities, weak government controls and corruption.

Compensation claims from past projects linger. For example, 50 years after the Kariba Dam was built on the Zambezi River, in what is now Zambia, 57,000 people who were resettled to make way for the dam are asking the World Bank and other parties for compensation because their new agricultural lands are less productive, according to the International Rivers Network.

To address such issues, industry associations and lending institutions have retooled their evaluation procedures for large hydro dams, and have started to apply new construction guidelines developed by a discussion forum, the World Commission on Dams. The World Bank also takes more account of environmental and social issues in its planning. It has developed a strategy to evaluate water use in all its aspects rather than considering energy production in isolation, and has established a complaints procedure for affected communities.

"Certainly within the Bank there is a trend now towards large hydro, and also internationally," said Daryl Fields, a water researcher at the World Bank. "Industry has stepped up to the plate - they are more confident that people are looking at environmental and social issues more rigorously."

But environmental watchdogs, like Environmental Defense and the International Rivers Network, still question whether these new mega-dams will significantly improve electricity supplies to the rural and urban poor in Africa, or whether the power will primarily serve large industrial users and the urban affluent.

"An acceptable balance of funding and timing for energy development in rural versus urban and industrial regions has to be reached," said Terri Hathaway, Africa campaigner for IRN.

Environmentalists also say the huge investments required for giant dams will leave fewer funds available for small-scale power generation. They say micro-hydro and other renewable energy sources would be better options to increase electricity access in remote rural areas, where hooking up to the grid is economically unfeasible.

As a part of an overall funding package to increase power production in Congo, where only about seven percent of the population has access to electricity, the World Bank's money will cover construction of a new transmission line to Kinshasa, rehabilitation and extension of the electricity-distribution network, and delivery of electricity to Kinbanseke, a suburban district about 12 miles, or 20 kilometers, east of Kinshasa with 1.5 million residents.

The World Bank says that it is working with SNEL, the national power utility, to help the company develop more transparent practices and better financial procurement methods, and it is also financing a medical project to help prevent river blindness near the Grand Inga site.

Still, compensation claims stemming from the construction of the existing dams, Inga 1 and 2, have never been paid by the government, said Jacques Bakulu, leader of a local social and civil rights organization, Cepeco.

Two activist groups, Environmental Defense and Bank Information Center, which visited the neighborhood of the Grand Inga site last year, called the local climate "tense." Local organizations say they are not being adequately consulted by the project's partners.

Now the government is beginning a census to determine how many people will need to be resettled. These should include at least 8,000 people from villages near the site, Bakulu said.

It remains to be seen how a country still barely recovering from war can take on such a huge infrastructure project. Corruption continues to plague the new government of President Joseph Kabila, who shifted from heading a transitional administration to an elected one in December, forming what has been billed as the first truly democratic government in the country's history.

Despite the first signs of a return to political normality, peace is still maintained only by the most expensive peacekeeping force operated by the United Nations anywhere in the world.

The country's infrastructure, from its battered electricity system to its battered roads, keeps Congo's people among the poorest in the world.

Planning for Grand Inga is still in the early stages, and no final decision will be made until 2014. The World Energy Council and the World Bank say that they see the project advancing in tandem with government efforts to develop a national energy plan, while assuring that all necessary checks and balances will be in place to enable the project to be undertaken successfully.

"Energy projects are key to the peace process," Doucet said.

 


OVER VIEW



Updated: 2003/07/28