een wereldwijd elektriciteitsnet een oplossing voor veel problemen  GENI es una institución de investigación y educación-enfocada en la interconexión de rejillas de electricidad entre naciones.  ??????. ????????????????????????????????????  nous proposons la construction d’un réseau électrique reliant pays et continents basé sur les ressources renouvelables  Unser Planet ist mit einem enormen Potential an erneuerbaren Energiequellen - Da es heutzutage m` glich ist, Strom wirtschaftlich , können diese regenerativen Energiequellen einige der konventionellen betriebenen Kraftwerke ersetzen.  한국어/Korean  utilizando transmissores de alta potência em áreas remotas, e mudar a força via linha de transmissões de alta-voltagem, podemos alcançar 7000 quilómetros, conectando nações e continentes    
What's Geni? Endorsements Global Issues Library Policy Projects Support GENI
Add news to your site >>







About Us

Ivanpah Solar Electric Generating System

Mar 30, 2011 - energy.ca.gov

Docket Number:

07-AFC-5C
(Compliance Proceeding)
07-AFC-5
(Application For Certification)

 

Committee Overseeing This Case:

Jeffrey D. Byron, Commissioner
Presiding Member

James D. Boyd, Vice Chair
Associate Member

 

Hearing Officer: Paul Kramer

 

Key Dates

General Description of Project

On August 31, 2007, Solar Partners I, LLC, Solar Partners II, LLC, Solar Partners IV, LLC and Solar Partners VIII, LLC (Solar Partners) submitted a single Application for Certification (AFC) to the California Energy Commission to develop three solar thermal power plants and shared facilities in close proximity to the Ivanpah Dry Lake, in San Bernardino County, California on federal land managed by the Bureau of Land Management (BLM). The proposed project would be constructed in three phases: two 100-megawatt (MW) phases (known as Ivanpah 1 and Ivanpah 2) and a 200-MW phase (Ivanpah 3). The three plants are collectively referred to as the Ivanpah Solar Electric Generating System (ISEGS) and would be located in:

  • Southern California's Mojave Desert, near the Nevada border, to the west of Ivanpah Dry Lake
  • San Bernardino County 4.5 miles southwest of Primm, Nevada, 3.1 miles west of the California-Nevada border
  • Township 17N, Range 14E, and Township 16N, Range 14E

Project Description

The proposed project includes three solar concentrating thermal power plants, based on distributed power tower and heliostat mirror technology, in which heliostat (mirror) fields focus solar energy on power tower receivers near the center of each heliostat array. Each 100-MW site would require approximately 850-acres (or 1.3 square miles) and would have three tower receivers and arrays; the 200-MW site would require approximately 1,600-acres (or 2.5 square miles) and would have 4 tower receivers and arrays. The total area required for all three phases would including the administration building/operations and maintenance building and substation and be approximately 3,400-acres (or 5.3 square miles). Given that the three plants would be developed in concert, the proposed solar plant projects would share the common facilities mentioned above to include access roads, and the reconductored transmission lines for all three phases. Construction of the entire project is anticipated to begin in the first quarter of 2009, with construction being completed in the last quarter of 2012.

graphic simulation of Ivanpah I solar facility

Process Description

In each solar plant, one Rankine-cycle reheat steam turbine receives live steam from the solar boilers and reheat steam from one solar reheater located in the power block at the top of its own tower. The reheat tower would be located adjacent to the turbine. Additional heliostats would be located outside the power block perimeter road, focusing on the reheat tower. Final design layout locations are still being developed. The solar field and power generation equipment would be started each morning after sunrise and insolation build-up, and shut down in the evening when insolation drops below the level required to keep the turbine online.

Each plant also includes a partial-load natural gas-fired steam boiler, which would be used for thermal input to the turbine during the morning start-up cycle to assist the plant in coming up to operating temperature more quickly. The boiler would also be operated during transient cloudy conditions, in order to maintain the turbine on-line and ready to resume production from solar thermal input, after the clouds pass. After the clouds pass and solar thermal input resumes, the turbine would be returned to full solar production. Each plant uses an air-cooled condenser or "dry cooling," to minimize water usage in the site's desert environment. Water consumption would therefore, be mainly to provide water for washing heliostats. Auxiliary equipment at each plant includes feed water heaters, a deaerator, an emergency diesel generator, and a diesel fire pump.

Electricity would be produced by each plant's Solar Receiver Boiler and the steam turbine generator. The heliostat mirrors would be arranged around each solar receiver boiler. Each mirror tracks the sun throughout the day and reflects the solar energy to the receiver boiler. The heliostats would be 7.2-feet high by 10.5-feet wide (2.20-meters by 3.20-meters) yielding a reflecting surface of 75.6 square feet (7.04 square meters). They would be arranged in arcs around the solar boiler towers asymmetrically.

Each solar development phase would include:

  • a natural gas-fired start-up boiler to provide heat for plant start-up and during temporary cloud cover;
  • an air-cooled condenser or "dry cooling," to minimize water usage in the site's desert environment;
  • one Rankine-cycle reheat steam turbine that receives live steam from the solar boilers and reheat steam from one solar reheater located in the power block at the top of its own tower adjacent to the turbine; and
  • a raw water tank with a 250,000 gallon capacity; 100,000 gallons to be used for the plant and the remainder to be reserved for fire water.
  • a small onsite wastewater plant located in the power block that treats wastewater from domestic waste streams such as showers and toilets;
  • auxiliary equipment including feed water heaters, a deaerator, an emergency diesel generator, and a diesel fire pump.

Transmission

Ivanpah 1, 2 and 3 would be interconnected to the Southern California Edison (SCE) grid through upgrades to SCE's 115-kV line passing through the site on a northeast-southwest right-of-way. Upgrades would include a new 220/115-kV breaker and-a-half substation between the Ivanpah 1 and 2 project sites. The existing 115-kV transmission line from the El Dorado substation would be replaced with a double-circuit 220-kV overhead line that would be interconnected to the new substation. Power from Ivanpah 1, 2 and 3 would be transmitted at 115-kV to the new substation.

Natural Gas

Natural gas supply for ISEGS would connect to the Kern River Gas Transmission Company (KRGT) pipeline about 0.5 miles north of the Ivanpah 3 site.

Water Use and Discharge

Raw ground water would be drawn from one of two wells, located east of Ivanpah 2, which would provide water to all three plants. Each well would have sufficient capacity to supply water for all three phases. Actual water is not expected to exceed 100 afy for all three plants. Groundwater would go through a treatment system for use as boiler make-up water and to wash the heliostats. No wastewater would be generated by the system, except for a small stream that would be treated and used for landscape irrigation.

Energy Commission and Bureau of Land Management Joint Review Process

The BLM and the Energy Commission have executed a Memorandum of Understanding concerning their intent to conduct a joint environmental review of all three plants in a single National Environmental Policy Act (NEPA)/California Environmental Quality Act (CEQA) process. It is in the interest of the BLM and the Energy Commission to share in the preparation of a joint environmental analysis of the proposed project to avoid duplication of staff efforts, to share staff expertise and information, to promote intergovernmental coordination at the local, state, and federal levels, and to facilitate public review by providing a joint document and a more efficient environmental review process.

Under federal law, the BLM is responsible for processing requests for rights-of-way to authorize the proposed project and associated transmission lines and other facilities to be constructed and operated on land it manages. In processing applications, the BLM must comply with the requirements of NEPA, which requires that federal agencies reviewing projects under their jurisdiction consider the environmental impacts associated with the proposed project construction and operation.

As the lead agency under CEQA, the Energy Commission is responsible for reviewing and ultimately approving or denying all applications to construct and operate thermal electric power plants, 50 MW and greater, in California. The Energy Commission's facility certification process carefully examines public health and safety, environmental impacts and engineering aspects of proposed power plants and all related facilities such as electric transmission lines and natural gas and water pipelines.

The first step in the Energy Commission's review process is for staff to determine whether or not the AFC contains all the information required by its regulations. When the Energy Commission determines the AFC is complete, staff will begin data discovery and issue analysis phases. At that time, a detailed examination of the issues will occur.

Energy Commission Facility Certification Process

The Energy Commission's facility certification process carefully examines public health and safety, environmental impacts and engineering aspects of proposed power plants and all related facilities such as electric transmission lines, natural gas pipelines, etc. The Energy Commission is the lead agency under the California Environmental Quality Act (CEQA) and has a certified regulatory program under CEQA. Under its certified program, the Energy Commission is exempt from having to prepare an environmental impact report. Its certified program, however, does require environmental analysis of the project, including an analysis of alternatives and mitigation measures to minimize any significant adverse effect the project may have on the environment.

For Questions About This Siting Case Contact:

Joe Douglas
Project Manager
Siting, Transmission and Environmental Protection (STEP) Division
California Energy Commission
1516 Ninth Street, MS-2000
Sacramento, CA 95814
Phone: 916-653-4677
Fax: 916-654-3882
E-mail: jdouglas@energy.state.ca.us

For Questions About Participation In Siting Cases Contact:

Public Adviser
California Energy Commission
1516 Ninth Street, MS-12 Sacramento, CA 95814
Phone: 916-654-4489
Toll-Free in California: 1-800-822-6228
E-mail: PublicAdviser@energy.state.ca.us

News Media Please Contact:

Media & Public Communications Office
Phone: 916-654-4989
E-mail: mediaoffice@energy.state.ca.us


OVER VIEW



Updated: 2003/07/28