First Segment of SCE’s Renewable
Energy Transmission Project Approved
Mar 1, 2007 Business Wire
New Lines Eventually Could Tap
Enough Renewable Energy to Power Almost Three Million
California Homes
ROSEMEAD, Calif.--(BUSINESS WIRE)--The
California Public Utilities Commission (CPUC) today
approved Southern California Edison’s (SCE) application
to build segment one of the Tehachapi renewable
transmission project.
When all phases are developed, the
Tehachapi project will include a series of new and
upgraded high-voltage transmission lines capable
of delivering 4,500(a) megawatts (MW) of electricity
from wind farms and other generating companies that
are proposed for northern Los Angeles and eastern
Kern counties.
SCE has proposed constructing the
Tehachapi project in 11 segments to coincide with
the development of independently owned wind farms.
Today’s decision approves the first of three segments
sometimes referred to as the Antelope project, pending
approval by the U.S. Forest Service. The first segment
includes the construction of a 26-mile, 500-kilovolt
transmission line connecting SCE’s Antelope Substation
in Lancaster with the utility’s Pardee Substation
in Santa Clarita. The new line is expected to be
operational in early 2009.
A CPUC decision on segments two and
three is expected later this month. SCE will file
an application in June of this year to build the
remaining segments.
“The Tehachapi project will strengthen
and enhance SCE’s transmission system by creating
a new path for renewable energy to meet the increasing
electricity demand of Southern California electricity
customers,” said Ron Litzinger, SCE senior vice
president of transmission and distribution.
Litzinger said that this favorable
decision is an important step in SCE’s efforts to
deliver electricity from wind farms in eastern Kern
County in support of meeting California’s renewables
portfolio standard and greenhouse-gas reduction
goals.
Last December, SCE signed a 1,500
MW wind contract, the largest in U.S. renewable
history, with Alta Windpower that relies on development
of the full Tehachapi renewable transmission project.
Today’s commission approval is an important first
step in assuring this and other Tehachapi contracts
result in viable renewable energy projects.
The Tehachapi project is part of SCE’s
five-year $4 billion transmission expansion program
designed to ensure that Southern California has
the robust power delivery system needed by a growing
region.
(a) One MW is enough power to serve
approximately 650 average homes. However, the actual
output of wind energy projects may be limited due
to weather conditions.
An Edison International (NYSE:EIX)
company, Southern California Edison is one of the
nation’s largest electric utilities, serving a population
of more than 13 million via 4.7 million customer
accounts in a 50,000-square-mile service area within
central, coastal and Southern California.