een wereldwijd elektriciteitsnet een oplossing voor veel problemen  GENI es una institución de investigación y educación-enfocada en la interconexión de rejillas de electricidad entre naciones.  ??????. ????????????????????????????????????  nous proposons la construction d’un réseau électrique reliant pays et continents basé sur les ressources renouvelables  Unser Planet ist mit einem enormen Potential an erneuerbaren Energiequellen - Da es heutzutage m` glich ist, Strom wirtschaftlich , können diese regenerativen Energiequellen einige der konventionellen betriebenen Kraftwerke ersetzen.  한국어/Korean  utilizando transmissores de alta potência em áreas remotas, e mudar a força via linha de transmissões de alta-voltagem, podemos alcançar 7000 quilómetros, conectando nações e continentes    
What's Geni? Endorsements Global Issues Library Policy Projects Support GENI
Add news to your site >>





About Us

North-South power link to be studied

Jul. 25, 2011 - irishtimes.com

Minister for Energy Pat Rabbitte with Owen Lewis, chief executive of the Sustainable Energy Authority of Ireland, at the announcement that Ireland has received a Star of Energy Efficiency Award for improving the energy performance of Irish homes.Photograph: Maxwells

MINISTER FOR Energy Pat Rabbitte has appointed three international experts to a commission to examine whether there is a case for building all or part of the North-South high voltage electricity interconnector underground, and the cost involved in such a project.

Bo Normark, president of Swedish firm Power Circle, has been appointed chairman of the commission and Odd-Håkon Hoelsæter, former chief executive of Norwegian electricity grid company Statnett, and Ronnie Elmans, a Belgian electric power professor, have been appointed members.

They must submit a report within six months on the case for and the cost of running power lines underground between Meath and Tyrone along all or part of the 400kV line. The report is expected to be submitted in the autumn.

Proponents of the interconnector say it is needed to improve competition in the electricity market and the security of supply.

The commission was established following the collapse last June of the planning process for the interconnector which was estimated to cost €280 million.

An error in the original application for the line through Meath, Cavan and Monaghan forced the State’s electricity network operator Eirgrid to withdraw the application during a Bord Pleanála hearing into the issue.

A review found incorrect information was supplied by ESB International.

The commission will consider the routes proposed by Eirgrid.