  
                           FERC Approves New Transmission Development 
                            Approach
                          Feb 26, 2009 - SustainableBusiness.com News 
                          Two transmission companies owned by TransCanada (NYSE: 
                            TRP) have proposed a new model for developing much 
                            needed electricity transmission in the U.S.  
                          Chinook Power Transmission, LLC and Zephyr Power 
                            Transmission, LLC have agreed to provide half of the 
                            capacity on their proposed new transmission lines 
                            to wind developers. The agreement is expected to help 
                            finance the transmission lines and convince utilities 
                            that the project is viable, while still leaving half 
                            of the transmission line capacity available for other 
                            power generators.  
                          The approach attempts to overcome a financing dilemma 
                            faced by independent companies wanting to build new 
                            transmission lines. Under current federal rules, they 
                            must open all access to that transmission line to 
                            a competitive bidding process, but they need to make 
                            significant investments prior to reaching that point. 
                           
                          In other words, they need to attract investors before 
                            they have a single customer. They also face a chicken-and-egg 
                            dilemma: power generators won't support a transmission 
                            line unless a utility says it needs the line to supply 
                            its customers, and utilities won't support a transmission 
                            line unless there is a power generator backing it 
                            up.  
                          On February 19, the Federal Energy Regulatory Commission 
                            (FERC) approved the new approach, allowing the two 
                            projects to go forward.  
                          FERC noted that it needs to show greater flexibility 
                            for such "merchant" power line projects, because the 
                            project developers assume all the market risks, and 
                            unlike electric utilities, they have no set pool of 
                            customers from which they can recover their project 
                            costs.  
                          The two projects include a 1,100-mile transmission 
                            line running from Medicine Bow, Wyoming, to just south 
                            of Las Vegas, Nevada, and a 1,000-mile transmission 
                            line that runs from Harlowtown, Montana, to the same 
                            ending point in Nevada.  
                          Each transmission line will have a capacity of 3,000 
                            megawatts (MW), which means that each line has an 
                            agreement with a wind power developer that plans to 
                            build 1,500 MW of wind power by the time the lines 
                            are completed in 2014. For comparison, at the end 
                            of 2008, Montana had only 272 MW of wind power capacity, 
                            while Wyoming had 676 MW of wind capacity. 
                           The companies did not name the wind power developers, 
                            although several wind developers reportedly were in 
                            favor of the proposal.  
                          The proposed transmission lines are significant for 
                            a number of technical reasons, as well, according 
                            to the Energy Efficiency and Renewable Energy (EERE) 
                            division of the Department of Energy. They will be 
                            the first transmission lines to ship large amounts 
                            of wind power from windy northern states to distant 
                            customers in the Southwest.  
                          To achieve this feat without losing too much energy, 
                            the lines will be high-voltage direct-current (HVDC) 
                            lines, operating at voltages of 500 kilovolts. Such 
                            HVDC lines can carry 3,000 MW of power on a single 
                            string of towers, while multiple towers would be needed 
                            for traditional lines using alternating current.  
                          According to TransCanada, each transmission line 
                            will cost about $3 billion, even though they follow 
                            the same path from Boise, Idaho, through Nevada. The 
                            construction of such "green power superhighways" is 
                            advocated in a white paper that was released on February 
                            17 by AWEA and the Solar Energy Industries Association. 
                           
                           
                            
                              
                             
                          
                         |