

Power Crisis: The Omission of Transmission
An issue paper on the U.S. Northeastern Blackout,
August 14, 2003
9.4.03 |
|
Elliot
Roseman, Principal, Power & Transmission,
ICF Consulting
|
Article Viewed 3733 Times
10 Comments
The recent massive power outage, affecting 50 million
people in seven states and Canada, stems from the way
in which the transmission system has been planned and
developed over the past 20-30 years. Transmission has
been a second-class citizen in the array of facilities
required to bring power reliably to consumers, with
scant attention paid to it until recently. Hopefully,
this event will be a wake-up call.
What are the root causes of the problem? While the
specific cause of the outage is still being determined,
the signs of substantial deterioration in the power
grid have been building for years. For example:
- The cost of transmission congestion in the most
developed market in the US, the PJM serving the
mid-Atlantic region, has grown nearly eight-fold
in the past three years, reaching $401million in
2002. Nationwide, the figure is in the billions.
Thus, the wholesale cost of power in 2002 was several
percentage points higher than it would have been
without congestion. Importantly, this trend points
to the increasing stress and loading of the transmission
system that leads eventually to a breakdown.
- According to the North American Electric Reliability
Council (NERC), power deals that could not be fulfilled
due to transmission constraints increased five-fold
to nearly 1,500 instances in 2002 compared to 300
in 1998.
- Major utilities have been seeing transmission
problems grow substantially. For example, the ability
to move power out of Entergy has deteriorated significantly
in recent years. Southern Company has estimated
the near-term need for $2-3 billion in transmission
investments, nearly doubling their current asset
base.
- According to the Electric Power Research Institute
(EPRI), roughly 2 million businesses have been losing
$46 billion per year in lost production due to power
outages and another $6.7 billion annually due to
power quality issues.
- According to the Edison Electric Institute (EEI),
transmission investment has fallen $115 million
per year for 25 years, from about $5 billion in
1975 to $2 billion in 2000 (in 1997 dollars).
- The Midwest Independent System Operator recently
released its first Transmission Expansion Plan,
identifying the need for at least $1.3 billion in
transmission upgrades and additions by 2007. Nationwide,
we estimate the need for new transmission investment
in the range of $30-60 billion in this decade.
What this all shows is that transmission system
operators have for years been pushing the transmission
system to its limits. These lines have very real constraints
in terms of their thermal capacity, stability (voltage
limits), and overall capacity to carry power. Operators
have frequently been pushing the more congested lines
to carry power right up to these limits in recent
years, as the system volume has grown sharply. Eventually,
something has to give.
Why has this situation been allowed to develop?
It’s been a combination of factors. One reason
is that transmission has been planned and approved
largely on a utility- and state-specific basis, without
sufficient regional coordination. Where there has
been regional coordination, such as in the PJM, the
regional entities have not had the authority to require
lines to be built, since the right to approve and
site power lines remains with the states, even when
the lines and the power they carry cross state lines.
At the state level, “not-in-my-backyard”
(NIMBY) concerns and its cousin, “build-absolutely-nothing-anywhere-near-anything”(BANANA)
have stymied construction. It’s almost like
having a separate Federal Aviation Administration
for each state.
A second reason is that utilities and independent
power producers in many parts of the country have
been dueling over who will build new transmission.
Except for a few regions such as the PJM, each utility
has had its own procedure. When new plants are built,
there is often a need for new transmission to accommodate
the power from those plants. However, the challenge
is often to distinguish between the need for transmission
to improve overall reliability versus the need for
transmission to accept power from these plants. The
Federal Energy Regulatory Commission recently issued
a ruling on generator interconnection that would help
resolve this question, but it has not yet been implemented.
Finally, there is no accepted standard for transmission
reliability. With power generation, we use the concept
of “reserve margin” to identify the extra
capacity to generate power that utilities should have,
over and above their expected demand for power. When
generation is projected to be short, utilities must
build plants or buy power to ensure that supply will
be sufficient. In transmission, however, there are
a patchwork of “best practices”, but nothing
that requires transmission to be built when the system
reaches a critical level. The operators are just left
to fend for themselves until the regulatory or political
logjam allows a new line to be built.
What should happen next? We recommend the following:
- A Federal “Marshall Plan” to build
or upgrade transmission capacity in the most congested
corridors in the country. The argument is at least
as strong for doing this as it was for the Federal
Highway System.
- Federal legislation to provide for “backstop”
authority to build new lines if states or regional
organizations defer in building lines that the FERC
or DOE believes are necessary.
- Greater regulatory certainty and regional responsibility
to assess the need for new transmission. Power flows
do not respect state boundaries, so state regulators
on their own cannot guarantee the reliability of
the grid. To balance state and regional/federal
authority, state regulators could be required to
jointly consider new transmission lines under the
auspices of a regional transmission organization
(RTO) or other entity.
- There should be incentives for performance. In
the United Kingdom, National Grid was able to retain
millions of pounds in exchange for reducing transmission
congestion by hundreds of millions. We should make
a similar bargain with our utilities.
- Greater use of new technologies such as FACTS
(Flexible Alternating Current Transmission System)
and superconductivity, so that we can push more
“juice” through the existing lines and
corridors.
- Greater use of private investment to supplement
the funds that utilities have available. Many utilities
are in difficult financial straits, and may wish
to leverage outside investment to maintain their
credit ratings. Pension funds, equity investors,
and others should be attracted to the fixed rates
and attractive returns that transmission offers.
In the process, we should expect the cost of transmission
to rise, leading to slightly higher rates for consumers.
But this would be a cheap insurance policy to buy.
Isn’t this a small price to pay to avoid blackouts
of the type that happened recently and to lower the
costs of congestion? Now more than ever, the answer
is yes.
Copyright 2004 CyberTech, Inc.
Readers Comments
Date |
Comment |
Wallace Brand
9.4.03 |
A few years ago,
a study by Arthur D Little suggested that while
the average historic cost of transmission and
distribution was $500 per kW, the current cost
was $1,260 per kW not including substations which
would add another $50 to $300 per kW. I have been
using $1,500 per kW but my numbers area few years
old. Do you have a durrent number that would approximate
the cost, per kW of adding transmission to make
up for the lag in construction of transfmission
following 1989 or 1992 when FERC was given the
authority to compel utilities to wheel the energy
of other utiliities or Independent Power Producers
over their transmission line and ownership of
transmission no longer conferred monopoly power
in the wholesale market?
You say the $100 billion in new transmission
construction would result in a "small"price
rise in the cost of electric power. The current
average cost nationwide, the last time I looked,
was about 7¢ a kWh overall for industrial, commercial
and residential service, and 8¢ on average for
residential service only. I agree with you that
new transmission, by relieving congenstion would
significantly reduce the cost of wholesale energy.
But I believe the cost of the new transmission
would exceed by far those savings. If the retail
cost were to go up as much as 3¢ to 5¢ per kWh,
that would likely exeed the cost of electric
power from fuel cells which are one of the kinds
of distributed generation. They would not need
either transmission or distribution lines and
their installation would reduce the load on
the transmission system. Over time, when sufficient
DG had been installed there would no longer
be the danger of cascading transmission line
outages. Along with that benefit, we would get
a virtual elimination of toxic pollution, an
great increase in the kind of reliability we
need for the digital age where blinks and voltage
sags of just a few microseconds will cause a
computer to crash, we would be able to add generation
in small increments more nearly approximating
local load growth, there would be no need to
add transmission lines snaking through the wilderness
nor through Connecticut suburbs, there would
be real competition in electric power supply,
and they could be a lower price. It seems to
me that the cost of transmission is rappidly
rising but DOE says that the production/cost
curves of fuel cell production would sharply
decline with an increase in volume.
If you agree with me on this point, would
it not make sense to switch to a decentralized
system design from a centralized design. The
latter was an excellent design for the last
one hundred years. But now that the system planner
has in his tool kit the option of tiny but extremely
efficient fuel cells, is it not time to plan
decentralized bulk power supply systems?
Regards,
Webrand.
|
F.Allen Morgan
9.9.03 |
It seems to me,
much of the criticism of the transmission system,
is due to its success. An underutilized system,
is one we spent to much money on. Any machine
that can operate without interruption for 20 years,
is a great machine. As much as the blackout showed
faults in the system it also showed that a cascading
blackout can be isolated and stopped. We all have
lived through nature inspired blackouts, yet we
don't clamour for a redesign of the distribution
system - why is that? Perhaps, we should focus
more on isolating grids, rather than designing
the perfect - monolithic "overbuilt" system.
I'm not accusing this author of this, but
how many other parties "talking up" the blackout
are really trying to sell product or services??
I saw within 2 days of the blackout, DSM providers
touting their product as blackout preventers.
|
Jack Ellis
9.9.03 |
You analysis
includes several examples where cost savings can
be realized but it overlooks the costs of new
facilities. As Mr. Morgan points out, transmission
congestion is not necessarily a bad thing. A transmission
system that is never congested is overbuilt and
underutilized. Consumers are forced to pick up
the tab for this overbuilt network since they
don't have the option of using a less expensive
transportation system.
You also omit any discussion of alternatives
to building more transmission, such as siting
new power plants more effectively, adopting
more aggressive conservation and demand management
strategies, and installing distributed generation.
All are valid alternatives that may provide
more timely, cost-effective congestion relief
than attempting to site, fund, design and build
new wires.
Your reference to the Federal Interstate Highway
system is not appropriate. While many physical
goods can cost-effectively be moved over long
distances, electricity generally cannot. It
is usually cheaper to build generating facilities
close to demand centers and transport fuel than
it is to generate close to fuel supply and move
power over long distances. Moreover, siting
generation close to demand reduces the power
system's vulnerability to atural disasters and
terrorist threats.
Jack Ellis
|
Robert O. Johnson
9.9.03 |
The article presents
an interesting collection of capacity needs and
reasons why such a situation has developed. In
addition to the infrastructure problems presented,
there is an overriding economic reason for neglect
of development in transmission capacity. Operating
in an ostensible atmosphere of "deregulation,"
transmission remains the most heavily regulated
(largely under FERC), and presents the least appealing
potential for investment. The other two major
segments of the electrical utility industry, generation
and distribution, continue to offer varying amounts
of appeal for profits, depending on circumstances
of local markets.
Unless a federally funded "Marshall Plan"
for transmission construction is created, which
appears unlikely in current circumstances, capital
and system organization must come from the private
sector. This will require a combination of revisions
in FERC authority & policy, and mechanisms
to allow (and possibly guarantee or subsidize)
profits by private investors.
Additional "distributed generation" by utilities,
to offset the peak demands on transmission systems,
face the same barrier. Capacity to offset transmission
peaks will by definition fulfill a peaking function.
Unless subsidized or provided economic guarantees
of minimum electrical production, investment
will not be attracted. Distributed generation
at the homeowner level remains relatively at
micro-industry capacity, requiring growth of
two and a half orders of magnitude to meet incremental
generation capacity needs. This is, of course,
many years ahead.
If we are to address the transmission problem
in the near future, we are left with the one
alternative of addressing the political &
economic circumstances of the transmission industry.
Given the inertia of public institutions and
public apathy toward direct subsidy of the energy
industry, this is a formidable task. It does,
however, offer the only current route to addressing
this situation.
Bob Johnson, SolarInsights LLC
|
Lorin Black
9.9.03 |
Dear Mr. Roseman,
the one flaw in many of the discussions regarding
the bulk transmission system in the USA is the
failure to recognize that the Transmission System
was planned and developed on the basis of locating
the generation close to the load and supplying
the power over relatively short transmission lines.
Along comes the Federal Government with what they
think is a better idea and all of a sudden we
are switched over to sending power over long distances
to the load being served...something the existing
Bulk Transmission System was never designed to
do. To add insult to injury, they are now saying
the transmission system is antiquated.
In your article above you say "According to
the North American Electric Reliability Council
(NERC), power deals that could not be fulfilled
due to transmission constraints increased five-fold
to nearly 1,500 instances in 2002 compared to
300 in 1998. " This is classic proof of the
fact that the system was not designed for this
purpose and is not being used in the way it
was originally intended to be used. To say the
system is old and antiquated is deceptive because
it is based on the new deregulatory environment,
not on how the transmission system was originally
designed. In short, the system may be old but
it is not antiquated, it is only being mis-used.
The real cause of the blackouts in New York
and elsewhere is the Federal Regulators who
chose not to plan their proposals properly and
instead trusted the open market to resolve issues
such as transmission congestion which didn't
appear until Deregulation was in full tilt.
We should not blame our utilities for not doing
their jobs, but the people who made these foolhardy
decisions in the first place. The height of
arrogance is emblazoned on the name of the FERC
888 NOPR that started this whole mess. It comes
from the address of the Federal Energy Regulatory
Commission itself!
It will cost billions of dollars to plan and
design our bulk transmission system to provide
power over long distances, a considerably different
concept from before deregulation started. Take
my word for it: "It will not be economical or
efficient to do so!" and if you think putting
mandatory reliability concepts into place will
change anything, then God Bless You because
you will need it.
I take great pride in the hard work and planning
that has taken good care of the service territory
my company serves. It is at times a thankless
job, but it doesn't matter, because I know all
of the people whom I work with have sacrificed
many long hours working to provide outstanding
service to the community around them. I wish
the people at First Energy well as they try
to recover from this latest outage and the regulatory
snafu that surrounds them.
"PLANNING INFLUENCED BY FEDERAL CHAOS IS NOT
PLANNING...IT'S AN OUTAGE WAITING TO HAPPEN!"
Lorin A. Black, Jr. Principal Engineer System
Planning Department El Paso Electric Company
El Paso, Texas
LBlack1@EPElectric.com
|
Martin Koller
9.10.03 |
Dear Mr. Roseman.
In item 5 of "what should happen next" you
mention new technologies to be applied in order
to put more juice through the existing luines.
At this point I'd like to mention storage. Storage
could be applied to transport the energy during
low load hours, store it, and consume it during
peak hours. This kind of levelling of the energy
flow would increase the capacity of the transmission
system dtastically.
One possibility to store electrical energy
is CAES (compressed air energy storage), a technique
that was applied first in 1978 by the Alstom
Company in the Huntorf plant in Germany.
Martin Koller Alstom (Switzerland) Ltd martin.koller@power.alstom.com
|
John Sheppard
9.10.03 |
These are all
great comments on a serious problem. Mr. Roseman
indicates that congestion has increased eight
fold during the last three years to a $401 million
dollar market. Has anyone considered that the
congestion model is flawed?
The load hasen't grown eight fold in three
years, maybe the congestion market is being
gamed.
|
Vytau Virskus
9.10.03 |
In order to develop
a comprehensive solution a broader view must be
taken, which would include exploring most of the
points made above. In fact, it will be necessary
to step back and review the current energy policy
and regulatory structure which does not promote
distributed generation. I am not speaking of base
load mini-plants (although fuel cells will have
a part to play in the future), which are far more
expensive to operate than a conventional coal
or nuclear plant. I am referring to conventional
fueled .5 to 1.0 MW units that can be installed
in many of the millions of small industrial and
commercial buildings that populate our most intensively
populated areas of the country. Many of them already
have small stand-by generators, required by fire
codes) that can only feed the emergency lights
during a power outage.
Various energy strategy descriptives have
come into vogue in recent years, like "renewable
energy", and "sustainable energy", and "distributed
generation", but it may be time for a new concept
such as Diversified Capacity.
Generation providers have no incentive to
promote the installayion of small generating
units (i.e. industrial, institutional, commercial)
into the system. LDC's, along with their affiliates,
do not promote the expansion of interruptable
tariffs to to provide displacement capacityduring
high peak periods, PUC's do not require appropriate
economic incentives for interruptable tariffs,
and there are no federal incentives. In addition,
retail electric providers are not required to
offer any interruptable rate programs that could
provide additional displacement capacity. Finally,
there are no code requirements or economic incentives
for displacement capacity (stand-by/displacement
generators ) to be installed in new construction
which would reduce the growth of capacity requirements,
therefore transmission requirements, for peak
periods.
One issue that always seems to be given short
shrift in discussions about generation and transmission
is Demand Side Mamagement. Anyone in the demand
side industry knows that energy consumption
can be reduced by as much as 40% - even more
- with the technology that grew lqargely out
of the Energy Policy Act of 1992. (Policy does
make a difference) Also, electric demand can
be reduced by 30-40% (100% if displacement strategies
are included). All of this can be done (and
IS done every day) with off-the-shelf technology
such as converting to T8 lighting, installing
varible speed drives, and integrating building
operations with the new generation of internet-based
energy management systems, which allow viewing
energy consumption and demand in real time.
Generation and transmission problems must
be addressed, but Diversified Capacity and Demand
Side Management must be part of the short and
long term solution - and maybe should be the
first place to start.
Vytau K. Virskus Millenium Energy Company
|
TERRY MEYER
9.19.03 |
SMELLS OF CORPORATE
WELFARE
|
TERRY MEYER
9.19.03 |
While Mr. Roseman
didn't come right out and suggest building transmission
at taxpayer expense to be used for corporate profit,
the discussion got way too close for me.
Sure, airlines, railroads, and trucking have
always had their subsidies in the form of infrastructure,
but is that any excuse?
Raise my taxes for socialized profits if you
must, just don't insult my intelligence by using
the term "deregulation" in the same article.
Terry Meyer "All power to the people."
|
|