
Nationalizing the Grid
Feb 06, 2011 - Phillip G. Harris
and Jack McCall - Mechanical Engineering Magazine
The U.S. is blessed with abundant renewable energy,
from wind in west Texas to sunlight in the western
deserts. And the nation is rapidly putting that clean
energy to work. Although most forecasts project annual
load growth of only 1 percent for the foreseeable
future, renewable power’s share of net generation
is projected to double by 2035.
But this power cannot be put to work unless it can
be economically transmitted to load centers. At present,
a key deficiency inhibiting the development of our
renewable energy sector is America’s balkanized
power grid: the largely isolated Eastern, Western,
and Texas interconnections. Only relatively small,
bilateral dc links currently exist between any two
interconnections—a mere 2,000 megawatts of
combined power transfer. And the three interconnections
have never been integrated.
Uniting these interconnections has been a goal for
some in the power industry for decades. But the Federal
Energy Regulatory Commission recently approved a
project designed to break this longstanding transmission
bottleneck and create a power-marketing hub that
will provide developers of renewable—and conventional—generation
with expanded regional and national markets in which
to sell their power. This project, called the Tres
Amigas SuperStation, will be located in Clovis, N.M.,
close to large amounts of established and potential
renewable generation, and in its first phase, slated
to begin construction in 2012, will support the 5,000
megawatts of power transfer capacity.
What’s more, the Tres Amigas project will
be a technological wonder. The project will employ
ultra-efficient, high-capacity dc superconductor
cables coupled with voltage-source converters in
what will be, in essence, a superconductive electricity
pipeline.
High temperature superconductors used in power transmission
are perfect direct current conductors. Wires made
from superconductor materials are over 100 times
more powerful than copper or aluminum wires of the
same size and they can transmit power with zero energy
loss when carrying direct current. The lack of resistance
makes it possible, indeed practical, to construct
dc superconductor cables with virtually any desired
power transmission capability.
The power density and efficiency advantages drive
system economics, and they are fundamental to the
reason that underground superconductor cables can
achieve cost parity with overhead alternating current
power lines over long distances while also delivering
superior returns on investment. In addition to eliminating
energy losses in transmission, superconductor cables
are compact, lightweight, and emit no heat or electromagnetic
fields, and they are particularly easy to install,
even in close proximity to other underground infrastructure.
The right of way needed to move 5,000 megawatts using
a superconducting electricity pipeline is significantly
smaller than that of conventional 765 kV transmission
lines.
Power cables employing superconductor wires are
available from several commercial producers and have
demonstrated their reliability and performance in
in-grid sites around the world. Such cables have
been installed in New York City, Long Island, and
Albany, N.Y.; Columbus, Ohio; Detroit; Tokyo, and
South Korea. While all installations to date have
been for ac applications, applying this established
technology to dc transmission is straightforward.
In dc applications in particular, modern power electronics
have paved the way for superconducting electricity
pipelines to become a significant operational solution
for transmission operators around the world. The
technology can be used for such diverse applications
as collecting wind turbine output from onshore and
offshore wind farms; collecting renewable energy
from solar and geothermal rich areas; enabling the
delivery of renewable power to distant major population
centers, including regions that have less productive
renewable resources; and transferring power from
region to region to take advantage of seasonal and
daily power generation and load profiles.
Nationalizing the Grid - Superconducting cables
Compared to traditional high voltage power lines,
superconducting cables are
much more compact.
Direct current power transmission itself is not new:
it has been used for decades around the world to
move large amounts of power from a single source
of power generation to one load center. While a
few multi-terminal systems using conventional cables
have been built, they were very difficult to implement.
But recently, multi-terminal technology based on
new power electronic designs incorporating voltage-source
converters has become available. VSC technology
provides greater control and flexibility and, most
important, enables dc lines to connect to multiple
generation sources and multiple areas of electrical
demand.
Direct current terminals employing VSC technology,
however, are available only at mid-level voltages
in the range of 100 to 300 kV. By comparison, ultra-high
voltages (around 800 kV) are used for conventional
point-to-point dc transmission. Thus, to be used
in high power transmission, the lower voltage levels
require the use of very high currents. But transmitting
high currents long distances through conventional
aluminum or copper conductors results in considerable
resistive losses.
Superconductor power cables bypass that limitation
by providing the ability to carry very high levels
of current with zero electrical loss. The combination
of a VSC-based multi-terminal dc system and superconductor
cables makes for a compelling new transmission option,
uniquely suited to transmitting renewable energy
over long distances with multiple collection and
distribution points. In the target applications,
superconductor dc cables have higher lifecycle returns
on investment because of their efficiency and operational
advantages.
The Tres Amigas SuperStation will employ this technology
toward an exciting goal. The SuperStation will make
it practical, and economical, to “firm up” intermittent
and variable renewable energy by taking advantage
of geographical diversity and energy storage, such
as the onsite batteries at Tres Amigas or systems
such as compressed air energy storage. This capability
greatly enhances the value of new generation, creating
additional economic incentives for its development.
Tres Amigas also will expand the geographic reach
of markets, offering new opportunities to take advantage
of load and resource diversity, which will reduce
costs. For example, at present, marginal prices for
energy in the three U.S. interconnections typically
diverge because these three markets operate in isolation.
Studies that Tres Amigas submitted during FERC proceedings
showed that marginal energy prices do vary significantly
between the Southwest Power Pool (in the Eastern
Interconnection), ERCOT and the WECC. Our studies,
during sample time intervals, showed that energy
prices vary by more than $50 per MWh for over 2,000
hours per year between CAISO and ERCOT, over 1,600
hours per year between ERCOT and the Palo Verde hub,
over 1,500 hours per year between SPP and the CAISO,
and over approximately 800 hours per year between
ERCOT and the SPP. The key conclusion is that significant
opportunities exist to bring lower cost power to
market by allowing more efficient producers access
to the market.
Nationalizing the Grid - The Tres Amigas SuperStation
Superconducting cables will enable the Tres Amigas
SuperStation to move electricity
among the three interconnected grids.
Just as important is that the Tres Amigas SuperStation
will enhance the value of transmission investments
made in the region by allowing power to move freely
between the interconnections. Tres Amigas will
permit power to move to and from different markets,
expanding the potential use of the existing transmission
grid and future additions. Tres Amigas should also
provide system planners new opportunities to improve
the efficiency and reliability of the electric
system at a lower overall cost.
Also, the reliability of the electric system in
the area around Tres Amigas will be improved. Tres
Amigas will connect the three asynchronous grids
at a robust station with backup power and voltage-source
converter technology that will provide substantial
reactive power to the transmission system in each
of the interconnections. VSCs can rapidly control
both active and reactive power independently. The
reactive power will be controlled separately at each
synchronous interconnection independent of the voltage
levels on the other synchronized systems.
By using VSCs, Tres Amigas will not place restrictions
on each ac network’s minimum short-circuit
capacity.
The self-commutation feature of VSC technology will
permit the set of three different phase voltages
to be synthesized. Because VSC converters themselves
have no reactive demand, Tres Amigas will be able
to control reactive power for regulation in each
separate ac system. The real-time dynamic support
of each ac system will be managed based on each system’s
separate and individual needs, thus improving stability
and transfer capability, and most likely reducing
losses on each connecting ac system.
Finally, the VSC will provide black start capability
to each interconnection separately. Tres Amigas will
appear, electrically, to each interconnection as
a large generator. The value of this to the long-distance
ac transmission lines planned for the region surrounding
Tres Amigas is significant. Although specific engineering
analysis of each line interconnecting to Tres Amigas
will need to be carried out, intuitively we can predict
that the technology that Tres Amigas is deploying
will solve many voltage, reactive support, stability,
and dynamic control problems that long-distance ac
lines connected to large intermittent generation
resources create.
It may sound futuristic, but the groundbreaking
for this project is actually close at hand. With
the recent signing of vendor contracts with CH2M
Hill, Xtreme Power, Burns & McDonnell, ZGlobal
Inc., and Viridity Energy Inc., the design and build-out
of the Tres Amigas SuperStation is near fruition.
The vendor agreements that Tres Amigas has completed
in recent months cover equipment, proprietary trading
platforms, and transmission system planning. Tres
Amigas is in the final stages of selecting the vendors
for the detailed engineering design and construction
services, as well as the supplier for the SuperStation’s
high-voltage dc technology.
Nationalizing the Grid - Thick copper cables and
slender ribbons of superconducting material
When chilled by liquid nitrogen, slender ribbons
of superconducting material
can carry as much electricity as thick copper cables.
When completed, the power conversion technology at
the Tres Amigas SuperStation will be a vast improvement
over the equipment used at most of the existing
ac/dc ties in the United States. It will apply
advanced and proven power grid technologies such
as high-voltage direct current superconductor power
cables, voltage-source converters, and energy storage
systems. Tres Amigas also will be the first high-capacity
system to connect all three of America’s
power grids, transmitting gigawatts of power from
region to region through the nation’s first
renewable energy market hub.
It will be the first step toward a green—and
continent-spanning—grid.
PICK UP AND DROP OFF
Superconductor electricity pipeline systems have
a broad scope of application. The superconductor
dc cable functions as a virtual bus-bar that can
carry a set amount of power across its length.
The VSC terminals are then able to inject power
onto the line, or pull power off the line in precisely
controlled amounts. This operation would be akin
to valves on a gas pipeline or on- and off-ramps
on a highway.
One possible use of that capability is long-distance
power transmission. For instance, a superconductor
electricity pipeline system could consist of several
linked loops of long-distance superconducting cable,
each with discrete points of connection to the ac
grid. (Connecting such a pipeline in loops increases
reliability, since maintenance work or unavailability
in one section would not prevent power from flowing
from one location to another.) Traditional ac transmission
would be utilized to collect power from geographically
adjacent wind farms and provide a common point of
connection to the pipeline at converter stations.
For example, 250 MW would be injected into a 5,000
MW superconductor dc cable at 20 locations as it
passes through the wind-energy-rich upper Midwest,
and 500 MW would be delivered to each of ten cities
on the East or West Coast.
IN FOR THE LONG HAUL
Superconductor electricity pipelines can be the most
efficient option for long-haul transmission, whether
in ac or dc grids. In all applications, high-temperature
superconductor cabling cuts power losses by a factor
of two or three when compared with conventional
transmission options. This results in improved
return on investment, and reduced pollution and
carbon emissions.
These advantages underpin the growing market for
HTS cabling. For example, in the United States, the
world’s first transmission-voltage cable system
has been operating successfully near New York City
since April 2008. This 138 kV system is now a permanent
part of Long Island Power Authority’s primary
transmission corridor. At full capacity, LIPA’s
power cable system is capable of transmitting up
to 574 MW of electricity and powering 300,000 homes.
The cabling for the LIPA installation was designed,
manufactured, and installed by Nexans. National Grid
and American Electric Power energized distribution-voltage
superconductor cable systems in their commercial
power grids in Albany, N.Y., and Columbus, Ohio,
respectively, in 2006.
In the summer of 2010, Nexans completed the first-ever
successful demonstration of an HVDC high temperature
superconducting cable operating at 200 kV. This prototype
cable, together with a newly designed termination,
passed a series of tests based on CIGRE (International
Council on Large Electric Systems) recommendations.
In October LS Cable Ltd. of South Korea announced
the purchase of 3 million meters of American Superconductor’s
Amperium high-temperature superconducting wire for
fabrication into transmission cables.
Just last year, AMSC received its first commercial
order from LS Cable for approximately 80,000 meters
of its Amperium wire to manufacture a 22.9 kV (distribution
voltage) ac cable system that will be installed in
a Korea Electric Power Corp. substation near Seoul.
Rated at 50 megawatts, that cable system will be
0.5 kilometer long, making it the world’s longest
distribution-voltage superconductor cable system.
LS Cable also is actively developing a 154 kV (transmission
voltage) ac superconductor cable system. KEPCO, which
is Korea’s only power grid operator, has forecasted
the wide deployment of superconductor power cables
in the Korean grid starting in the 2012-2013 time
frame.
Phillip G. Harris is chairman and chief executive
officer of Tres Amigas, LLC, in Sante Fe, N.M.
Jack McCall is director of high temperature superconductor
transmission and distribution systems for American
Superconductor in Devens, Mass.
|