High voltage transmission lines across
the political boundaries of north
African countries have started as
early as 1952 when a 90 kV transmission
line was built between Algeria and
Tunisia. It has been followed by
a 220 kV line which was commissioned
in the year 1980 and a 150 kV line
in the year 1984.
Two transmission lines have been
constructed between Algeria and
Morocco, one commissioned in 1988
and the second 1992. According to
jointly agreed agreements between
the three countries, the maximum
exchange is not to exceed 150 MW
between Algeria and Tunisia and
200 MW between Algeria and Morocco.
A feasibility study is being updated
for a project to interconnect the
power systems in Tunisia and Libya,
in order to exchange ta power with
a maximum of 150 MW in either direction.
The project would include the construction
of about 600 km of 220 kV transmission
lines, most of it in the territory
of Tunisia. It is planned that this
interconnection be commissioned
in the 1996.
The interconnection between Egypt
and Libya is being progressively
implemented. Both countries are
extending the 220 kV network to
gradually reach the common borders.

Arab-Maghreb Interconnection
Of course, full interconnection
of the power systems of the five
countries would be effected by the
construction of a 500 kV (400 kV)
transmission system superimposed
on the 220 (150) kV transmission
lines which are now used for the
transfer or exchange of a certain
amount of power.
|