Time To Remove The Roadblocks To A National Transmission
Grid
Nov 17, 2010 - Gilbert E. Metcalf
- Investors.com
On the campaign trail, President
Obama is promoting his green jobs agenda as an
antidote to high unemployment. And though it's
an approach that doesn't always attract bipartisan
support, one aspect of it should — and has:
the construction of a true national electricity
grid.
One especially unusual and attractive aspect:
it's a green construction project that can be financed
privately. What's more, such investments, as Google
makes clear, will not need to be government-financed — just
one reason that "grid" improvements have
attracted rare, bipartisan support.
Few policies attract support from both Obama and
Newt Gingrich. The development of a national inter-connected
electricity grid is one of them. The president
has promoted what he describes as a "newer,
smarter electric grid" that "will make
our energy bills lower, make outages less likely
and make it easier to use clean energy."
Former Speaker Gingrich has chosen a different
emphasis — but reached the same conclusion. "You've
got to rebuild the electric grid," he said, "because,
as I keep telling all of my left-wing environmental
friends, if you want people to drive electric cars,
there has to be electricity."
Indeed, there's a bipartisan understanding that
adding new interstate high-voltage lines to connect
and expand what are now three barely linked regional
electricity distribution systems can both help
bring new, less-expensive power to parts of the
country where prices are high and serve as a transmission
highway to cities for wind and solar power, generated
in remote locations.
Over 50 years ago, President Eisenhower championed
an interstate highway system for its national security
and economic development benefits. Today, Susan
Eisenhower, chair of the Eisenhower Institute and
the president's granddaughter, has advocated a
built-out grid as a latter-day version of the interstate
highway system — infrastructure that sets
the stage for prosperity.
The electric power industry is on board, as well;
wary of power peaks and the risks of blackouts,
it seeks the reliability that an extended and improved
national transmission network would ensure.
Yet, over the past decade, during which we have
added 15,000 miles of new interstate natural gas
pipelines, we have added just 685 miles of new
high-voltage interstate electric power transmission
lines. Improving on that record will require two
key, related realizations: first, that an improved
and expanded grid can actually be financed privately
and second, that doing so will require crucial
public (i.e., regulatory) cooperation.
Traditionally, investments in our transmission
and distribution grid — a system built incrementally
over the past century by private utilities — have
been financed through retail payments for electricity.
This remains a robust and available revenue stream,
expected to total, over the coming decade, some
$2.6 trillion.
By comparison, I estimate — based
on projections of the North American Electric Reliability
Corporation — that investment costs for transmission
lines of 230kV or higher over that same period
will be $90.8 billion.
Even if these estimates are too conservative by
half, improving our transmission grid will cost
only 5% to 10% of our total expenditure on electricity
between now and 2018. For the average residential
customer in the United States, this translates
to as little as $5 a month and at most $10 a month
on their electric bill.
There are a number of ways that private investments
in the grid can be structured that will make public
financing unnecessary. One of the more promising
approaches is known as "transmission congestion
charging."
Here's how it works. Peaks in power demand allow
those who own high-voltage lines to earn a healthy
return by serving power-hungry utilities. If there
were no congestion on transmission lines, then
all electricity would be provided by the lowest
cost generators.
But congestion in areas of high demand, caused
by too much power flowing across too few lines,
requires system operators to shift from lower-cost
to higher-cost electricity. If private developers
can lay claim to the margins that this shift creates,
they will likely find investing in new transmission
lines to be an attractive business model.
In an ideal world, the full cost of private investment
in grid expansion would be covered by transmission
congestion charging. In the real world, however,
the numbers are unlikely to add up. Costs that
aren't covered, namely those associated with the
advance construction of spare capacity, can be
spread uniformly to users on a per-megawatt or
megawatt-hour basis or allocated directly to the
beneficiaries of new investment in transmission
capacity.
A clear system of cost-allocation is essential
for attracting private investment. And here government
has an important role to play. The patchwork quilt
of grid regulation — based in the 50 state
public utilities commissions, established when
power distribution was extremely local — today
poses a significant obstacle to interstate grid
investment.
Regulators may respond more to minor NIMBY objections
than to the benefits that an improved grid can
provide the overall economy — and faraway
cities. For example, in 1990, American Electric
Power proposed a 90-mile project spanning the West
Virginia/Virginia border. Gaining local approval
and rights-of-way for the project took 13 years;
constructing the line took less than three years.
Simply put, potential investors seek assurances
that new transmission lines won't be rejected by
states and localities after capital has been irretrievably
spent on planning and development. Although the
Electricity Policy Act of 2005 took the first steps
toward giving federal officials the right to preempt
state objections — through the establishment
of so-called National Energy Corridors — court
rulings since have blunted the legislation's impact.
The outline of a federal preemption regime that
is sensitive to state concerns has started to take
shape. Legislation proposed by New Mexico Sen.
Jeff Bingaman, chair of the Senate Energy and Natural
Resources Committee, recognizes the economic potential
for solar and wind power in the West, where an
improved grid will be necessary to accommodate
such intermittent power sources.
To date, however, legislation has stalled — and
has, moreover, been flawed by dividing federal
siting authority between the Department of Interior
and the Federal Energy Regulatory Commission, agencies
with different missions and sensibilities.
We need to give a lead agency the responsibility
for transforming and expanding the national grid,
even as it consults with others at both the state
and federal level. And we have to understand that
the value of a national grid outweighs parochial
concerns such as those of New England governors
who objected to high-voltage lines that could bring
wind-generated power from the Midwest into competition
with offshore wind turbines.
It's worth keeping in mind that the payoff for
breaking the regulatory logjam that has slowed
or blocked grid construction goes beyond keeping
on the lights, air-conditioners and computers in
New York, Chicago and Los Angeles. An improved
and extended grid could truly be the green jobs
creator that the Obama administration has sought
both in response to climate change and the economic
downturn. If only we could get started on it.
• Metcalf is a professor of economics at
Tufts University and a research associate at the
National Bureau of Economic Research. He is the
author of a recent report, "Financing a National
Electricity Grid: What Are the Issues?" (published
by the Manhattan Institute).