Mid-way through a hot, humid summer, electric 
                                      grid operators across much of the country 
                                      have managed increased demand for power 
                                      by coordinating their efforts to ensure 
                                      reliability and maintain system performance. 
                                    
Grid operators responsible for managing 
                                      the flow of wholesale power across the Eastern 
                                      Interconnection–an area that stretches from 
                                      the Rockies to New England and from Arkansas 
                                      to Manitoba–have all reported record levels 
                                      of electricity usage during this summer’s 
                                      extreme heat and high humidity.
                                    
 Thus far, their systems have met demand 
                                      with few problems, although some organizations 
                                      have asked consumers to conserve power during 
                                      periods of peak usage. The grid managers 
                                      credit coordinated efforts with their own 
                                      members and with other independent system 
                                      operators, or ISOs, for their continued 
                                      ability to meet high demand and to maintain 
                                      system performance and reliability. 
                                    
Their experiences so far this summer in 
                                      successfully meeting high demand for power 
                                      should prove valuable throughout the remainder 
                                      of the season, they added, as well as in 
                                      preparations to meet future demands on their 
                                      respective systems. 
                                    
During daily conference calls, representatives 
                                      of grid operators along the Eastern Interconnection 
                                      discuss the day’s outlook and share data 
                                      regarding projected peak demand for power 
                                      within each system. In addition, numerous 
                                      operating agreements between ISOs have improved 
                                      coordination, particularly at seams along 
                                      the borders of neighboring systems.
                                    
 Under the agreements, the ISOs share critical 
                                      operating data relating to the management 
                                      of reliability and relief of congestion 
                                      within their respective systems. The ISOs 
                                      also share day-today planning data to ensure 
                                      that each grid operator can recognize and 
                                      manage the effects of its operations on 
                                      adjoining systems. 
                                    
Improved coordination among ISOs also creates 
                                      opportunities to import or export power 
                                      from one system to another, as needed, to 
                                      meet demand for power. Grid operators across 
                                      the Eastern Interconnection have reported 
                                      new peak demands for power usage throughout 
                                      the summer’s extended heat wave. 
                                    
* PJM Interconnection, which operates the 
                                      power grid for all or parts of 13 states 
                                      and the District of Columbia, announced 
                                      on July 26 that it had successfully met 
                                      a peak demand for about 135,000 MW, a new 
                                      record. PJM’s previous record peak demand 
                                      was 130,574 MW, reached on July 18. 
                                    
* On Aug. 3, the Midwest Independent Transmission 
                                      System Operator, Inc. (Midwest ISO), which 
                                      manages the power grid for all or parts 
                                      of 15 states and the Canadian province of 
                                      Manitoba, successfully met a demand within 
                                      its reliability footprint of 131,434 MW, 
                                      topping the previous peak of 131,188 MW 
                                      set on Aug. 2. 
                                    
* The New York Independent System Operator 
                                      (NYISO) announced on July 26 that, for the 
                                      second straight week, high heat and humidity 
                                      drove statewide electricity usage to record 
                                      levels. NYISO officials recorded a peak 
                                      load of 32,075 MW on July 26, breaking the 
                                      previous week’s record of 31,741 MW. 
                                    
* ISO New England, Inc., (ISO-NE) which 
                                      operates the bulk power grid serving the 
                                      New England region, announced it had reached 
                                      an all-time high on July 27, topping out 
                                      at 26,922 MW. The previous record, of 26,749 
                                      MW, had been set on July 19. Prior to 2005, 
                                      New England’s record was 25,348 MW, set 
                                      in 2002. 
                                    
* Southwest Power Pool, Inc. (SPP), which 
                                      manages the power grid in all or part of 
                                      seven southwestern states, has experienced 
                                      high demand this summer as well. Non-coincidental 
                                      peak for July 22 was 38,852 MW, surpassing 
                                      the previous day’s peak of 38,612 MW. With 
                                      the unusually high demand levels in the 
                                      northeast, SPP has actually seen transmission 
                                      patterns moving south to north, which is 
                                      atypical for the summer months. 
                                    
One megawatt is enough electricity to power 
                                      about 800 homes, according to national averages. 
                                    
All told, NYISO, SPP, ISO-NE, PJM and the 
                                      Midwest ISO supply wholesale power to approximately 
                                      142 million people, roughly 48% of the U.S. 
                                      population.