Costs Of Argentina Power Transmission Line Soar 70%
Dec 
1 , 2009 - Dow Jones - Newswires
Authorities on Tuesday 
set aside an extra $512.5 million to complete construction of a power transmission 
line in northern Argentina, as costs have soared more than 70% over budget. 
The 
additional investment comes on top of the original $725 million cost of the 1,200-kilometer 
electric power transmission line, which will connect the country's northeastern 
power grid with the northwestern grid, uniting nine provinces with a population 
of about 8 million. 
The Washington, D.C.-based Inter-American 
Development Bank on Wednesday said it has agreed to pay out another $300 million 
to cover the cost overruns, in addition to the $580 million loan authorized in 
2006. 
The Argentine government will commit a further $212.5 
million to the project, on top of the $145 million it agreed to invest back in 
2006, the IDB said in a statement. 
That brings the total cost 
of the project to $1.24 billion. 
The higher cost of equipment 
and materials such as steel, aluminum and cement, as well as higher labor costs, 
have contributed to the overruns, the IDB said in a statement. 
The 
two sets of loans are for 25 years, with a five-year grace period at a variable 
interest rate, the IDB said. 
A spokesman for the Planning 
Ministry wasn't available for comment. 
-By Matthew Cowley, 
Dow Jones Newswires; +54 11 4103 6740; matthew.cowley@ dowjones.com